Times of Central Asia (Aug 2026, newly relevant): Ekibastuz Data Center Valley was absent from Kazakhstan's 2026 power forecast, faces a 2027 reserve-adjusted capacity deficit and depends on coal

The Times of Central Asia; subject: Kazakhstan Ministry of Energy, Kazakhtelecom, Firebird.ai · National energy planning for AI data centres · Kazakhstan (Ekibastuz, Pavlodar region)

Publisher
The Times of Central Asia
Original publication
2026-08-25
Source retrieved
2026-10-23
Event date
2026-08-25
Read original source

What happened

TCA reports that Data Center Valley near Ekibastuz, led by Firebird.ai and Kazakhtelecom, is planned to reach 1 GW, which could consume about 8.8 TWh a year (about 7% of current generation, per Qyzyq), with a first 50 MW facility due June 2027. Kazakhstan's 2025 generation shortfall was 1.5 TWh, met largely by Russian imports. The 2026 electricity forecast included no data-centre project; the ministry says they enter calculations from 2027. The official balance shows a 1.278 GW surplus in 2027 before reserves but a 2.366 GW deficit once required reserve is included. The key new plant, the 2.6 GW coal-fired GRES-3, is due 2029-2032 and not yet under construction. Data centres would use 2,300 m3 of water a day from the Satpayev Canal. No environmental-impact assessment is public and no major named customer contract has been announced.

Why it matters

Newly relevant because NVIDIA's Oct 22 post announces 1,000+ Vera Rubin GPUs in the Ekibastuz region next year. Transferable to U.S. states and counties weighing AI data-centre incentives: utility load forecasts, reserve margins, water sources and public environmental review are the decision points.

Evidence and measured results

Independent reporting with ministry responses, S&P Global capacity data and named experts. Not specific to NVIDIA hardware. Published Aug 25, 2026; Novastan (Oct 2) and DCD reporting on the coal-based plan were also opened and are consistent.

Limitations and uncertainty

Pre-dates NVIDIA's announcement; 1 GW consumption figure is a media estimate; Vera Rubin deployment may sit in a different phase or facility from the 50 MW first stage.

Put this evidence to work

Lighthouse Advisory interpretation, grounded in this source. Enriched 2026-10-23; this does not change the original publication date. Each role follows the same checklist so takeaways compare across sources.

Sales

Role takeaway
Customer problem
Governments promote AI data centres before power, water and environmental plans are public.
Stakeholders
  • Energy ministry or state utility commission
  • County officials
  • Residents
  • Data-centre developer
Discovery questions
  • Is the load in the utility forecast and reserve plan?
  • Where will cooling water come from?
  • Has an environmental assessment been published?
Value hypothesis
Interpretation: transparent power and water planning reduces delay and opposition risk.
Potential engagement
Power, water and public-disclosure readiness review for a planned AI compute site.
Unsupported claims
  • That Ekibastuz power is secured
  • Named customers for Data Center Valley

Pre-sales engineering

Role takeaway
Fit
Large GPU sites in grids with tight reserve margins.
Architecture and integration
Co-location with generation; dependency on new coal plant.
Prerequisites
  • Interconnection agreement
  • Reserve margin
  • Water rights
Constraints
  • 2.366 GW reserve-adjusted deficit in 2027
  • GRES-3 not before 2029
  • Plant wear
Security
Not addressed by the source.
Proof of value
  • Utility confirmation of firm capacity
  • Water-use modelling for cooling choice

Delivery

Role takeaway
Work
Phase capacity with power availability; publish environmental information.
Dependencies
  • Generation build-out
  • Grid upgrades
  • Regulatory approvals
Ownership
Developer and state operator with energy ministry.
Skills and adoption
Not addressed.
Governance checkpoints
  • Inclusion in national energy forecast
  • Environmental-impact assessment publication
Acceptance criteria
  • Proposed: firm power contract before each phase
  • Proposed: published EIA before construction of later phases
Risks
  • Delay from generation shortfall
  • Public opposition from lack of transparency
  • Emissions lock-in

Implementation considerations

Lighthouse Advisory interpretation across the operating dimensions a public-sector buyer must settle before this evidence becomes a design. Each note answers the question under its heading for this specific source.

Architecture and integration

What must connect, and where does the AI sit in the workflow?

Siting next to coal generation reduces transmission losses but ties capacity to ageing plants with high wear rates.

Governance

Who approves, reviews and stays accountable for outcomes?

Data-centre demand entering national planning only in the year the first facility opens shows a planning gap; public transparency on water and emissions is lacking.

Security and privacy

What data, permissions and controls need testing?

Not addressed.

Accessibility and workforce

Who is affected, and what skills or accommodations follow?

Local residents report lack of information on water, power and environmental impact.

Procurement

What should contracts, pricing and exit terms secure?

Not addressed.

Operating model

Which teams own the service once it runs?

Capacity delivery depends on new generation that is years away; reliability risk during winter peaks.