From the VAST Data edition of November 26, 2026
VAST webinar page (Dec 9, 2026): Lockwood to show a real 900 PB production system with 8,008 122 TB SSDs and simulated failure data
VAST Data · HPC and AI data centers; applicable to power-constrained university and research computing centers · Global
- Publisher
- VAST Data
- Original publication
- Undated event page (webinar Dec 9, 2026)
- Source retrieved
- 2026-11-27
- Event date
- 2026-12-09
What happened
VAST's event page for a Dec 9 webinar says Glenn Lockwood will use a real 900 PB system in production with 8,008 SSDs of 122 TB each to discuss what storage bandwidth costs in GPU power, potential savings from next-generation SSDs, ten years of simulated drive failures against that exact system, and failure detection and recovery across hundreds of servers. The production drive count (8,008) differs from the 7,920-drive configuration reported for VAST's SC26 simulation.
Why it matters
University and research data centers sizing large flash systems (e.g., TACC Horizon's 400 PB and NCSA Garnet's planned 50 PB raw VAST tier, both archived) are power-constrained; the webinar is a scheduled chance to question VAST's power and data-protection assumptions. Interpretation; no SLED data in the source.
Evidence and measured results
Read the event description and learning objectives. Compared drive counts with the archived Tom's Hardware SC26 report (7,920 SSDs, 180 enclosures of 44). No data or slides yet.
Limitations and uncertainty
Vendor marketing for a future event; customer unnamed; no publication date on the page; simulation results come from VAST, not an independent party; 8,008 vs 7,920 difference unexplained.
Put this evidence to work
Lighthouse Advisory interpretation, grounded in this source. Enriched 2026-11-26; this does not change the original publication date. Each role follows the same checklist so takeaways compare across sources.
Sales
Role takeaway
- Customer problem
- Power-constrained research data centers must size petabyte flash tiers without starving GPUs of power or risking data loss on very large drives.
- Stakeholders
- Research computing director
- Facilities and power planner
- Storage architect
- CIO
- Discovery questions
- What is your storage power budget relative to GPU power?
- What drive capacities are you planning for next refresh?
- What parity scheme and rebuild window do you accept today?
- Value hypothesis
- Interpretation: larger SSDs may free facility power for compute if data protection is designed for their rebuild times.
- Potential engagement
- A briefing session after the Dec 9 webinar comparing VAST's assumptions with the site's power and durability requirements.
- Unsupported claims
- Specific data-loss odds for any customer system
- Power savings at a named SLED site
- Identity or performance of the 900 PB system
Pre-sales engineering
Role takeaway
- Fit
- Large shared flash tiers at power-limited campuses and national research centers.
- Architecture and integration
- VAST DASE with system-wide erasure coding on high-capacity QLC SSDs.
- Prerequisites
- Site power and cooling budget
- Target bandwidth requirement
- Failure-domain design
- Constraints
- Vendor modeling only
- Production system unnamed
- Rebuild time grows with drive capacity
- Security
- Not addressed.
- Proof of value
- Ask VAST to state which configuration (8,008 or 7,920 drives) each result uses
- Request the failure-rate inputs to the simulation
- Compare modeled rebuild times with observed rebuilds on an existing system
Delivery
Role takeaway
- Work
- Capture webinar assumptions into the site's storage design review and power plan.
- Dependencies
- Webinar materials
- Site power data
- Vendor configuration details
- Ownership
- Storage architecture lead with facilities.
- Skills and adoption
- Staff review erasure-coding and rebuild-time trade-offs for high-capacity drives.
- Governance checkpoints
- Design review comparing modeled and site-specific durability
- Facilities sign-off on storage power budget
- Acceptance criteria
- Proposed: documented storage watts per usable PB for the chosen design
- Proposed: documented rebuild-time estimate per drive size
- Risks
- Relying on unreproduced vendor simulations
- Configuration mismatch between model and deployment
Implementation considerations
Lighthouse Advisory interpretation across the operating dimensions a public-sector buyer must settle before this evidence becomes a design. Each note answers the question under its heading for this specific source.
Architecture and integration
What must connect, and where does the AI sit in the workflow?
High-capacity SSDs trade bandwidth and rebuild time for capacity per watt; protection must scale with drive size.
Governance
Who approves, reviews and stays accountable for outcomes?
Design reviews should ask vendors to reconcile modeled and production configurations before relying on simulated risk figures.
Security and privacy
What data, permissions and controls need testing?
Not addressed beyond data-durability framing.
Accessibility and workforce
Who is affected, and what skills or accommodations follow?
No direct effect.
Procurement
What should contracts, pricing and exit terms secure?
Request vendor durability modeling inputs and production references as part of large flash procurements.
Operating model
Which teams own the service once it runs?
Larger drives lengthen rebuilds; operations need monitored failure handling and clear escalation.
Publication history
- 2026-11-26VAST Data · Issue 172 resources
Stable resource ID: vast-lockwood-900pb-webinar-8008-ssds-20261209